Santa Barbara County Air Pollution Control District

Frequently Asked Questions
Rule 802 - Nonattainment Review


* means that the question is taken out of Section 8 of the NSR Staff Report.

For more information or assistance, call the Engineering Division at (805) 961-8800, or e-mail us at engr@sbcapcd.org.


Approved SIP

Q: Sources may be subject to rules that are in the approved SIP even if those rules are not current district rules. If there are two versions of a rule, one SIP approved and submitted for inclusion in the SIP, which version of the rule does a facility have to comply with?

A: Rule 802 Section G.5 states "The control officer shall issue an Authority to Construct for major new stationary source or major modification to a stationary source, which is subject to this rule, only if all District Regulations contained in the State Implementation Plan submitted to the EPA are being carried out in accordance with that plan." However, EPA has authority to enforce the SIP approved version of a rule. Therefore, in cases where there are two versions of a rule, one approved into the SIP and the other submitted by the District to EPA awaiting approval into the SIP, sources must comply with both versions of the rule. Where the rules are in conflict, the source must comply with the most stringent provisions of both rules. EPA has been working with Santa Barbara APCD to prioritize EPA review of rules that have been submitted for SIP approval. This should help to minimize disparities between district rules and SIP approved rules.

BACT Threshold

Q: Does the BACT threshold of 25 pounds per day or greater allow for decreases during the application? During subsequent applications that are considered the same project for modified sources?

A: According to the ARB, the intent for changeover to the PTE basis (H&SC 40918) was to eliminate the possibility of "netting out" of BACT. As such, only the increases are evaluated against the 25 lb/day threshold. This also applies to the APCD's definition of project. In both cases, if an application proposed emission decreases they may not be used to reduce the PTE for determining BACT applicability.

Banked emission reductions vs. netting

Q: Do all emission reductions have to clear through the bank or can an operator use on-site emission reductions to meet emission reduction requirements?

A: This question is really one of netting. Can a source "net out" of emission offset requirements by using on-site emission reductions to reduce the net emission increase of a modification to below the emission threshold that triggers offsets? The answer is yes. However, be aware that for nonattainment pollutants the APCD uses the dual source definition. This means that for the modification, an operator cannot use on-site emission reductions to net out of an offset requirement. Such reductions may, however, be used as offsets at the offset trading ratio. For a new modification where the modification does not trigger nonattainment offset requirements by itself, but where the entire source may trigger offsets, and for attainment pollutant offset requirements, an operator can use on-site reductions to avoid offsets. See the later discussion in this section on the issue of netting.

Determining Offset Ratios

Q: hen measuring the distance from the source supplying offsets to the source using offsets to determine offset ratios, will the APCD measure between emission units or stationary source boundaries?

A: When determining if the location of offsets is within 7.5 miles of the location of the ATC source as specified in Rule 802 Table 4, the distance is determined by measuring between the two stationary source boundaries.

Emission Increases, Grandfather Provisions.

Q: For offsets, is any grandfathering proposed? For example, a source could have a net emission increase above 10 tons per year since 1990 which would not require offsetting under current rules. However, under the proposed rule any emission increase at such source would require the source offset the full 10 tons per year.

A: The source would be required to offset the full net emission increase.

Netting for Nonattainment Pollutants (BACT)

Q: Can a source net out of Best Available Control Technology for nonattainment pollutants?

A: No. Netting pertains only to new source review triggers that are based on net emission increase. Netting therefore cannot be used for nonattainment Best Available Control Technology because a trigger based on potential to emit is proposed for use as the Best Available Control Technology trigger for nonattainment pollutants.

Netting for Nonattainment Pollutants (Offsets)

Q: Can a source net out of offsets for nonattainment pollutants?

A: The dual source definition applies to the offset trigger for nonattainment pollutants. This is current APCD practice. Thus, the determination of whether offsets are triggered for nonattainment pollutants is a two step process. First, the net emission increase of a proposed modification is calculated. If the modification by itself triggers offsets, then offsets apply. If the modification by itself does not trigger offsets, then the net emission increase from the modification is added to net emission increase for the entire source. If the net emission increase for the entire source exceeds the offset trigger, then offsets are required. Netting is allowed on the calculation of source wide net emission increase. That is, creditable decreases at a source can be used to reduce the net emission increase resulting from a modification to avoid triggering emission offset requirements.

Netting for Nonattainment Pollutants (Replacements)

Q: Do the proposed rules allow a source to subtract the actual emissions of the equipment being replaced when calculating the NEI of the modification in the first step of the dual source calculation?

A: A source can subtract actual emissions (based on the definition of Actual Emission Reductions in Rule 102) of the equipment being replaced provided the new equipment is the same type as the old. For example, a boiler replacing a boiler, or an I.C. engine for an I.C. engine. Netting out is not allowed in the case of one emissions unit type 'x' replacing emission unit type 'y' under the guise they both perform the same function. For example a source would not be allowed to subtract emissions from a boiler if they were replacing it with a turbine even though both products produce steam. This is the only exception allowed under the dual source definition. As always, deductions are always allowed for all reductions in calculating the facility wide NEI.

Examples of the replacement netting out policy follow (note in the following examples the replacement does not qualify for exemption under the "equivalent routine" exemption provided by Rule 202D.9).

Example 1

Given:

1990 NEI = 0 (source was all pre 1990)

Boiler X 15 tpy PTE, 10 tons actual

Boiler Y replacement boiler, 15 tpy PTE

  Find: If offsets are required.

Solution:

First find NEI of Modification (Step 1)

Mod NEI = 15 - 10 = 5

Offsets not triggered.

Next find Facility Wide NEI = I + (P1 - P2) -D (Step 2)

FW NEI = 15 + (0 - 0) - 10 = 5 tpy

offsets not triggered

Example 2

Given:

Source's NEI before modification = 15 tpy (from equipment other than X & Y)

Boiler X Pre 1990, 12 tpy actual, 20 tpy of permitted emissions

Boiler Y replacement boiler, 11 tpy permitted emissions

Find: If offsets are required.

Solution:

First find NEI of Modification (Step 1)

11 - 12 = -1 tpy.

Since the NEI of the modification is less than the Offset threshold no offsets are required by the modification half of the dual source definition.

Next find facility wide NEI = I + (P1 - P2) - D (Step 2)

 

FW NEI = 11 + (15 - 0) - 12 = 14

14 tons is greater than the trigger level offsets are required, but since the modification itself was a decrease (-1 tpy), no offsets would be required.

Example 3

Given: NEI = 20 tons per year (from equipment other than X & Y)

Boiler X Pre 1990, 15 tpy PTE, 6 tpy actual emissions

Boiler Y replacement, 15 tpy PTE

Find: If offsets are required.

Solution:

Modification NEI (Step 1)

NEI Mod = 15 - 6 = 9

Offsets not triggered

Facility Wide NEI = I + (P1 - P2) - D (Step 2)

15 + (20 - 0) - 6 = 29 Offsets Triggered

29 tons must be offset

New Sources

Q: When is a source no longer considered a "new source", once the PTO for the new source is issued? How is the NAR BACT criteria applied if a new source has obtained an ATC permit, initiated construction, is still in the SCDP phase and is submitting ATC Modification applications. Are the ATC Modification application(s) treated as a modified source or still as the new source under Section C.1?

A: Rule 102 defines a "new source" as any stationary source which will emit any air contaminant not previously emitted at that location. That determination was made during the initial ATC permit phase. Until the source obtains a PTO for the equipment and processes subject to the ATC, any subsequent ATC Modification applications received during the SCDP phase are treated as being part of the new source. The applications are not considered a modified source under the provisions of Section C.1 (i.e., there is no evaluation needed for what the "project" is).

Offset Liability

Q: Please clarify how the dual source definition would apply when the project itself triggers offsets and the applicant also proposes to create on-site reductions.

A: As clarified in the staff report, if the project itself triggers offsets then offsets are required and netting is not allowed (this only applies to NAR review). Any decrease proposed by the applicant must be processed as an ERC through the Source Register. This applies to all scenarios - including one where the decrease is proposed to eliminate existing NEI (P1) only.

Offset Liability (Decreases)

Q: Would the APCD require a source with pre-rule-adoption NEI greater than the threshold to offset its NEI even when it applies for an emission decrease?

A: With the new lower offset trigger there may be sources that already have pre-existing NEI's greater than the threshold that have never been mitigated through offsets. Any source in this situation will be required to offset the entire NEI at their next modification. However, sources are not required to offset their NEI if they apply for a modification that results in a decrease in emissions.

Offset Liability (Full Amount).

Q: If a source triggers offsets, does it have to offset just the amount of the net emission increase above 10 tons per year, or the full net emission increase?

A: The source must offset the full net emission increase. However, a source must only provide offsets for increases that have not already been offset. If source with a 12 tpy NEI proposes a project that would result in an additional 2 tpy NEI, the source must offset all NEI that has not already been offset. Thus if a source has already offset the 12 tpy NEI, they must now offset the additional 2 tpy.

 

For more information or assistance, call the Engineering Division at (805) 961-8800, or e-mail us at engr@sbcapcd.org.

Return to Frequently Asked Questions

Rule 802